Cross CTL Harvest Starting Wednesday, 04/28
Cross CTL Harvest Starting Wednesday, 04/28
Cross CTL Harvest Information
Note: There will be reduced parking at Oak Creek Trailhead on Wednesday 04/28
Approximate Closure Duration: 6 weeks
Closed Roads: 6021.1, 6021.3, portions of 6021
Closed Trails: No authorized trails will be affected; all unauthorized trails leading into the harvest area will be closed; neighborhood access will be closed
Haul Routes: 6021 to 600 Road
Detours: None
Size: 15.1 ac
Harvest Method: Cut-to-length: ground-based harvester/forwarder
Prescription: Commercial thinning (several small entries totaling 15.1 acres)
Reason For Harvest: Remove slow growing, diseased, and suppressed trees to allow continued growth of remaining conifers. Harvest designed to maintain long-term Urban Fringe Research Project prescription
Stand Age: 32
Additional Considerations: None
Consistent w/ McDonald-Dunn Forest Plan? Yes